How to Run a Project Premortem in 60 Minutes
At a glance
A premortem is a short session at the start of a project where the team imagines it has already failed and writes down why. Because the failure is assumed, people name risks they would normally keep to themselves.

The steps
-
Set the scene in one sentence
Open with a fixed prompt: "It's six months from now. This project failed. Not a small miss; it clearly failed." Give the date and the goal that was missed so everyone pictures the same outcome.
-
Have everyone write reasons alone
Give the group eight minutes of silent writing. Each person lists every reason they can think of for the failure, one per sticky note or line. Writing alone first keeps the loudest voice from setting the agenda.
-
Collect reasons one at a time
Go around the room and take one reason per person per round until the lists run out. Write each on a shared board without debate. Duplicates are useful: they show where worries overlap.
-
Group and rank the risks
Cluster similar reasons into themes such as dependencies, unclear ownership, or optimistic estimates. Then have each person vote for the three themes most likely to happen and most damaging if they do.
-
Assign a counter-move to the top risks
For the top three to five themes, agree on one action that makes the failure less likely or catches it early: a check-in date, a spike, a backup supplier, a clearer owner. Each action gets a name and a date.
-
Schedule a risk check
Put a 15-minute review on the calendar a few weeks in to look at the list again. Risks change once work starts, and a premortem that is never revisited is just a worried meeting.
When to use it
A premortem fits best right after a plan is agreed and before much money or time is spent. It is especially useful when:
- The project is large, visible, or hard to reverse.
- The team is new to the domain or to each other.
- Everyone seems confident and nobody has voiced concerns.
- A similar project has struggled before.
Common mistakes
The session only works if people feel safe naming uncomfortable risks. These habits undermine it:
- The project sponsor arguing with each risk as it is raised.
- Skipping the silent writing and going straight to discussion.
- Listing risks without agreeing on any actions.
- Running it after the plan is locked, when nothing can change.
How to tell it's working
Good premortems produce at least one risk the project lead had not considered, and at least one change to the plan. If the list only repeats known concerns, the group may not feel free to speak.
Later in the project, look back at the list. When problems arrive that were named in the premortem and already had a counter-move, the session paid for itself.
Common questions
What is the difference between a premortem and a risk assessment?
A risk assessment asks what might go wrong. A premortem assumes failure has happened and asks why, which makes people more specific and more candid.
How many people should be in a premortem?
Five to ten works well. Fewer limits the range of views; more makes it hard to hear everyone in an hour.